Wednesday 12 February 2014

Plumbing

Yesterday the plumbing was done, along with the site fence being erected, and a water tap installed. SS expects the concretors to be on site for the rest of the week getting the formwork ready to pour the slab as next Thursday 20th Feb our frames are suppose to be delivered. Hopefully we will also see a loo and the sediment control fence put up as well.