Pre-Build Time Line

Date                               Day          Process

3rd May 2013                                  Offer made and accepted on land

23rd May 2013                                 Paid $950 deposit to Rawson Homes for tender

28th May 2013                                 Contracts on land exchanged

23rd June 2013                                Tender presentation

24th June 2013                   0            Signed tender & paid $3000 deposit

25th June 2013                   1            Land settled, Advised colour pack sent, CSO will ring this week

26th June 2013                   2            Colour pack received

27th June 2013                   3

28th June 2013                   4            Our CSO contacted us

29th June 2013                   5    

30th June 2013                   6

1st July 2013                      7

2nd July 2013                     8

3rd July 2013                      9

4th July 2013                     10

5th July 2013                     11

6th July 2013                     12

7th July 2013                     13

8th July 2013                     14          CSO emailed,advised we dont require landscape plans for estate

9th July 2013                     15

10th July 2013                   16

11th July 2013                   17

12th July 2013                   18

13th July 2013                   19

14th July 2013                   20

15th July 2013                   21

16th July 2013                   22          Trees on block chopped down

17th July 2013                   23

18th July 2013                   24          Pre-approval from bank received

19th July 2013                   25

20th July 2013                   26

21st July 2013                   27

22nd July 2013                  28          Advised by CSO that we should receive our plans early next week

23rd July 2013                  29

24th July 2013                  30

25th July 2013                  31

26th July 2013                  32           Received our 1st set of plans via email

27th July 2013                  33

28th July 2013                  34

29th July 2013                  35

30th July 2013                  36

31st July 2013                  37

1st August 2013                38

2nd August 2013               39          Signed off on shed/bedroom wall variation and emailed to CSO

3rd August 2013               40

4th August 2013               41

5th August 2013               42

6th August 2013               43            Appointment @ 11am to go over plans and make changes

7th August 2013               44            Changes faxed off to Head Office

8th August 2013               45            Finally received hard copies of 1st set of plans in mail

9th August 2013               46

10th August 2013             47

11th August 2013             48

12th August 2013             49

13th August 2013             50

14th August 2013             51

15th August 2013             52

16th August 2013             53             Received Check Plan Variations via email

17th August 2013             54             Deposit for pool paid

18th August 2013             55

19th August 2013             56             Emailed CSO back with changes to be made to variations

20th August 2013             57

21st August 2013             58             CSO rang to advise that house is too big for block of land. With                                                                    driveways and pool we are over by 42sqm

22nd August 2013            59             Went to chisholm to look at 2 storey house options

23rd August 2013             60             1/2 way mark for pre-build process!!!

24th August 2013             61              Meeting at Chisholm to discuss house options

25th August 2013             62

26th August 2013             63              Went to council with plans, advised ok to proceed with house
                                                           Updated check plan variations received, signed off on and                                                                             returned via email.

27th August 2013             64              Advised that it will be about 20 working days until our DA                                                                             quality plans are ready

28th August 2013             65

29th August 2013             66

30th August 2013             67

31st August 2013             68

1st September 2013         69

2nd September 2013        70               External colours submitted

3rd September 2013         71

4th  September 2013        72

5th September 2013         73

6th September 2013         74

7th September 2013         75

8th September 2013         76

9th September 2013          77             DA plans received - variation to driveway required

10th September 2013        78             Variation received and sent back. Back to drafting for                                                                           amendment. Revised DA plans received, signed and sent                                                                               back $7000 deposit paid.

11th September 2013        79

12th September 2013        80

13th September 2013        81

14th September 2013        82

15th September 2013        83

16th September 2013        84

17th September 2013        85

18th September 2013        86            Hunterwater wont endorse plans - tank to close to sewer

19th September 2013        87            Engineering plans now required to show tank wont interfere                                                                     with sewer. 2 weeks and they will be completed.

20th September 2013        88

21st September 2013        89

22nd September 2013       90

23rd September 2013       91          

24th September 2013       92           Finally recieved and email to make colour appointment

25th September 2013       93          Rang Tile Direct and YHC to arrange appointments

26th September 2013       94

27th September 2013       95

28th September 2013       96

29th September 2013       97

30th September 2013       98

1st October 2013            99            Engineer plans received  - ready for hunter water to approve

2nd October 2013          100

3rd October 2013          101        

4th October 2013          102           Hunter Water stamped plans. Plans lodged with Mine Subsidance

5th October 2013          103

6th October 2013          104

7th October 2013          105

8th October 2013          106

9th October 2013          107

10th October 2013        108        Mine subsidance stamped and sent plans back to Rawson

11th October 2013        109

12th October 2013        110

13th October 2013        111        Should receive plans back from Mine Subsidance

14th October 2013        112

15th October 2013        113        Should be ready to lodge at Council

16th October 2013        114        Plans from Mine Subsidance finally recevied. Plans express posted to                                                           council for DA approval

17th October 2013        115         LMCC should receive plans in mail. DA number recevied for pool.

18th October 2013        116          DA number allocated for house plans.

19th October 2013        117             Accent Carpets @ 10 am & Colour selections @ 1pm

20th October 2013        118

21st October 2013        119             Tile Direct @ 7:30am & YHC for electrical appointment @ 11am

22nd October 2013       120            Questioned Bal rating with rawson, down as bal 29.

23rd October 2013       121

24th October 2013        122          Sourced second opinion on bal rating and advised it should be lower

25th October 2013        123          Rawson said we could get another bushfire report completed

26th October 2013        124

27th October 2013        125

28th October 2013        126        New bushfire assessment completed and sent to council.Now bal 12.5

29th October 2013        127

30th October 2013        128       Received variation credit for bushfire rating reduction & variation for                                                              electrical

31st October 2013        129

1st November 2013       130       DA approval for house and pool received

2nd November 2013      131

3rd November 2013       132

4th November 2013       133

5th November 2013       134       New CSO assigned! Contract arrived in mail

6th November 2013       135

7th November 2013       136      Contract & CC form express posted back to Rawson

8th November 2013       137

9th November 2013       138

10th November 2013     140

11th November 2013     141        Bank received contract for loan - CC paperwork lodged

12th Novembe 2013      142

13th November 2013     143      CC issued - only took 2 days!!!

14th November 2013     144       Should finally receive colour selection variations - still waiting for 1/2                                                           of  them

15th November 2013     145

16th November 2013     146

17th November 2013     147

18th November 2013      148

19th November 2013     149

20th November 2013     150         Pool getting installed   delayed due to backlog

21st November 2013      151        Pool getting installed, Home Loan approved

22nd November 2013     152       Pool installation completed. Received our colour selections prices

23rd November 2013     153

24th November 2013      154    

25th November 2013      155      Signed off on colour variations - file off to drafting and estimating

26th November 2013      156

27th November 2013      157

28th November 2013      158

29th November 2013      159

30th November 2013      160

1st December 2013        161

2nd December 2013       162

3rd December 2013       163

4th December 2013       164      Rawson finally have all paperwork require for countdown to start

5th December 2013       165      Final Plans received - changes to window height from FFL needed

6th December 2013       166      Variation for window heights signed - plans need to be re-done :(

7th December 2013       167

8th December 2013       168  

9th December 2013       169      Received drawings of kitchen, laundry, pantry and bathrooms

10th December 2013     170

11th December 2013     171

12th December 2013     172

13th December 2013     173

14th December 2013     174

15th December 2013     175

16th December 2013    176

17th December 2013    178

18th December 2013    179

19th December 2013    180
     
20th December 2013    181         Rawson close down for xmas

6th January 2014         182

7th January 2014        183          Advised by CSO that plans wont be finished until mid Jan :(

8th January 2014        184

9th January 2014        185      

10th January 2014      186

11th January 2014      187

12th January 2014      188

13th January 2014      189

14th January 2014      190

15th January 2014      191       Final plans received - Construction period to commence